Frampton Court Court Road Frampton Cotterell Bristol South Gloucestershire BS36 2DW
Discharge of condition 3 (detailed design) attached to P22/03371/LB. Internal alterations to replace existing staircase, removal of internal wall to form two en-suite bathrooms.
Mayshill Farm Mays Hill Frampton Cotterell South Gloucestershire BS36 2NS
Discharge of Condition 3 (Detailed design) Condition 4 (Staircase details) and Condition 5 (Plaster details) attached to planning permission P22/06413/LB Internal and external works to include: replacement of missing external stone work; installation of replacement rainwater goods; repointing of...
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal application to discharge Requirement 20 (Watercourse Protection Plan) for Stage 10.1 of the authorised development.
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission for the discharge of Requirements 13 (4) Bird Collision Monitoring Strategy for Stage 10.1 of the authorised development
Land To The East Of Lyde Green Road Emersons Green South Gloucestershire
Non material amendment to permission P20/06681/F to amend the wording of conditons 5, 6 and 9 to allow development to commence on land within the public highway boundary prior to the discharge of these conditions.
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission to discharge of Requirement 6(1)(f) Emergency Response Plan for Flood Events for Stage 10.1 of the authorised development
Land East Of Cedar Lodge Charlton Common Brentry South Gloucestershire BS10 6LB
Erection of 29no. dwellings and associated works - Approval of Reserved Matters to be read in conjunction with outline permission P19/15643/O. Discharge of condition 20 (archaeological investigation) attached to P19/15643/O.
Plot 2 Central Park Goldcrest Way Severn Beach South Gloucestershire
Discharge of Condition 2 (CEMP) Condition 3 (Landscape and EMP) Condition 5 (Geoarchaeological work) Condition 6 (Badger survey) Condition 9 (Ventilation and extraction system) Condition 10 (Landscape and planting) Condition 11 (Contamination - risk assessment) Condition 12 (Contamination - Land...
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission to discharge of Requirement 6(1)(f) (Emergency Response Plan) for Flood Events for Stage 10.1 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Formal Submission to discharge of Requirement 6(1)(e) (Lighting Scheme) and Requirement 8 (Control of Artificial Light Emissions) for Stage 10.1 of the authorised development