Hinkley Point C Connection Project, between Bridgwater in Somerset and Seabank Substation, north of Avonmouth. The Project is in Somerset and across the administrative boundaries of the following planning authorities / highway authoriti...
Formal Submission for the discharge of Requirements 6(1)(g) Site Waste Management Plan for Stage 10.1 of the authorised development
Hinkley Point C Connection Project, between Bridgwater in Somerset and Seabank Substation, north of Avonmouth. The Project is in Somerset and across the administrative boundaries of the following planning authorities / highway authoriti...
Formal Submission to discharge Requirement 25 (Highway Signage Plans) for Stage 3.2 of the authorised development
Hinkley Point C Connection Project, between Bridgwater in Somerset and Seabank Substation, north of Avonmouth. The Project is in Somerset and across the administrative boundaries of the following planning authorities / highway authoriti...
Formal application to discharge Requirement 5(2)(b) Biodiversity Mitigation Strategy (BMS) for Stage 3.2 of the authorised development
Hinkley Point C Connection Project, between Bridgwater in Somerset and Seabank Substation, north of Avonmouth. The Project is in Somerset and across the administrative boundaries of the following planning authorities / highway authoriti...
Formal application to discharge Requirements 6(1)(e) and 8 (Lighting Scheme) for Stage 3.2 of the authorised development.
Hinkley Point C Connection Project, between Bridgwater in Somerset and Seabank Substation, north of Avonmouth. The Project is in Somerset and across the administrative boundaries of the following planning authorities / highway authoriti...
Discharge Requirement 16 (Fencing and Other Means of Enclosure) (FOME) for Stage 3.2 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
(Hinkley Point C Connection Project) discharge of Requirement 6(1)(a) (Soil Management Plan) for Stage 10.1 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Hinkley Point C Connection Project discharge of Requirement 6(1)(d) (Project Environmental Management Plan) for Stage 10.1 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
National Grid Hinkley C Connection Project Discharge of Requirement 18 (Contaminated land and Groundwater for) Stage 10.1 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Hinkley Point C Connection Project discharge of Requirement 5(2)(b) (Biodiversity Mitigation Strategy) for Stage 10.1 of the authorised development
Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth.
Hinkley Point C Connection Project discharge of Requirement 40 (Assessment of Noise Impacts) and Requirement 41 (Assessment of Vibration Impacts) for Stage 10.1 of the authorised development