North Kesteven District Council Planning Applications

Found 17 planning applications

21/1513/DISCON | Discharge of Conditions

Sir William Robertson High School Main Road Welbourn Lincoln Lincolnshire LN5 0PA

Application to discharge condition 3 (community use scheme) attached to planning permission 19/1280/FUL - Creation of an Artificial Grass Pitch (AGP) for school and community use with associated fencing, barriers and entrance gates plus associated porous asphalt surfacing for portable goals storage, pedestrian circulation access, vehicular maintenance and emergency access; floodlight system, erection of high maintenance equipment store, together with soft landscaping work involving the creation of grassed mound within playing field and screen planting.

Local Authority
North Kesteven District Council
Type
Approval (Discharge) of conditions (Discharge of Conditions)
Decision
Approved (Approved)
Application Received
21/09/2021
Application Validated
09/11/2021
Erection Landscaping Discharge Fence
21/1024/LDEXI | Existing Lawful Development Certificate

Land North East Of Scopwick Scopwick LN4 3PH

Certificate of Lawful development for an existing use in respect of the construction of approved access junction to B1188 and first section of road pursuant to 16/0410/VARCON - Application to vary conditions 3 (Scheme of landscaping and biodiversity enhancements), 4 (Scheme of protection for Great Crested Newts), 5 (Scheme of works to ensure that archaeological remains are preserved), 8 (Provision of wheel-washing facilities), 11 (Code of Practice) and 12 (Scheme of protection for trees and hedgerows) attached to planning application 14/0937/FUL - Development of a solar photovoltaic power generating installation with associated 132kv substation, transformer/inverter stations, internal access tracks, security fencing and landscaping - to allow phased commencement of development.

Local Authority
North Kesteven District Council
Type
Lawful Development Certificate (LDC) (Existing Lawful Development Certificate)
Decision
Approved (Approved)
Application Received
06/07/2021
Application Validated
06/07/2021
Construction Development Landscaping Trees Fence Lawful-Development
21/1166/DISCON | Discharge of Conditions

Installation Of High Voltage Direct Current (DC) Cables For The Viking Link Interconnector Project Between Proposed Landfall At Boygrift In East Lindsey To A Proposed Converter Station At North Ing Drove In South Holland

Application to discharge condition 14 (Archaeological Mitigation) attached to application 17/1200/FUL - Works to facilitate the Viking Link electrical interconnector with an approximate capacity of 1400 megawatts (MW) extending from Revsing, Jutland, (Denmark) to Bicker Fen, Lincolnshire (UK) comprising: - Installation of two (2) subsea high voltage direct current (DC) cables between Mean Low Water Springs (MLWS) and landfall at Boygrift in East Lindsey; - Installation of two (2) onshore DC cables between the landfall at Boygrift and the converter station at North Ing Drove in South Holland; - Construction of associated Temporary Construction Compounds (TCC) and Temporary Works Areas (TWA) and temporary vehicle access arrangements required for DC and AC cable installation; - Erection of converter station buildings together with the formation of internal roads, permanent access road from the A52, erection of security fencing, formation of landscaping with associated temporary construction compounds; - Installation of up to six (6) onshore high voltage alternating current (AC) cables between the converter station at North Ing Drove and the existing Bicker Fen 400 kilovolt (400kV) Substation owned and operated by National Grid Electricity Transmission Plc (NGET); - Installation of link pillars along the AC cable route for inspection and maintenance purposes, these will be contained within fenced areas; - Installation of two substation bays at Bicker Fen Substation to allow Viking Link to be connected to the National Grid electricity transmission system; - Installation of all associated drainage mitigation works; and - Installation of fibre-optic cable(s) with the high voltage AC and DC cables (A bay consists of switching equipment including circuit breakers, disconnector and measuring equipment. NGET will be providing Viking Link the space available to connect to Bicker Fen).

Local Authority
North Kesteven District Council
Type
Approval (Discharge) of conditions (Discharge of Conditions)
Decision
Approved (Approved)
Application Received
30/07/2021
Application Validated
30/07/2021
Erection Construction Landscaping Discharge Fence
21/0282/DISCON | Discharge of Conditions

Installation Of High Voltage Direct Current (DC) Cables For The Viking Link Interconnector Project Between Proposed Landfall At Boygrift In East Lindsey To A Proposed Converter Station At North Ing Drove In South Holland;

Application to discharge condition 5 (Landscape Restoration) attached to planning permission 17/1200/FUL - Works to facilitate the Viking Link electrical interconnector with an approximate capacity of 1400 megawatts (MW) extending from Revsing, Jutland, (Denmark) to Bicker Fen, Lincolnshire (UK) comprising: - Installation of two (2) subsea high voltage direct current (DC) cables between Mean Low Water Springs (MLWS) and landfall at Boygrift in East Lindsey; - Installation of two (2) onshore DC cables between the landfall at Boygrift and the converter station at North Ing Drove in South Holland; - Construction of associated Temporary Construction Compounds (TCC) and Temporary Works Areas (TWA) and temporary vehicle access arrangements required for DC and AC cable installation; - Erection of converter station buildings together with the formation of internal roads, permanent access road from the A52, erection of security fencing, formation of landscaping with associated temporary construction compounds; - Installation of up to six (6) onshore high voltage alternating current (AC) cables between the converter station at North Ing Drove and the existing Bicker Fen 400 kilovolt (400kV) Substation owned and operated by National Grid Electricity Transmission Plc (NGET); - Installation of link pillars along the AC cable route for inspection and maintenance purposes, these will be contained within fenced areas; - Installation of two substation bays at Bicker Fen Substation to allow Viking Link to be connected to the National Grid electricity transmission system; - Installation of all associated drainage mitigation works; and - Installation of fibre-optic cable(s) with the high voltage AC and DC cables (A bay consists of switching equipment including circuit breakers, disconnector and measuring equipment. NGET will be providing Viking Link the space available to connect to Bicker Fen).

Local Authority
North Kesteven District Council
Type
Approval (Discharge) of conditions (Discharge of Conditions)
Decision
Approved (Approved)
Application Received
26/02/2021
Application Validated
26/02/2021
Erection Construction Landscaping Discharge Fence
21/0428/CCC | County Council Consultation with NKDC

Villa Farm Folly Lane Norton Disney Lincoln Lincolnshire LN6 9JL

To construct an animal by-products processing facility to include two processing buildings for category 1 (and category 2) and category 3 material, associated ducting, ancillary boiler houses, covered filtration beds with flues, 25m high composite stack, water treatment plant, internal roadways, employee welfare buildings, stores, weighbridge, weighbridge kiosk, trailer park, visitor and staff car park, attenuation lagoons, clean water pond, landscaping, new vehicular access to folly lane, upgraded second access, 2.4m paladin fencing, change of use and alterations to the two existing dwellings to form ancillary offices and demolition of all other existing buildings

Local Authority
North Kesteven District Council
Type
Other (County Council Consultation with NKDC)
Decision
(Comments Made)
Application Received
18/03/2021
Application Validated
18/03/2021
Alteration Demolition Dwelling Landscaping Office Fence
19/1638/FUL | Full Application

Loudor Hotel 37 Newark Road North Hykeham Lincoln Lincolnshire LN6 8RB

Change of use from C1 to C1 & A3, internal alterations including a reduction in restaurant capacity from 48 to 40, widening of access, addition of extra car parking spaces including a disabled bay and staff parking and landscaping including acoustic fencing. (Resubmission of application 19/0884/FUL)

Local Authority
North Kesteven District Council
Type
Full planning consent (Full Application)
Decision
Approved (Approved)
Application Received
25/11/2019
Application Validated
28/11/2019
Alteration Landscaping Fence
19/1764/FUL | Full Application

North Hilltop Farmhouse The Heath Leadenham Lincoln Lincolnshire LN5 0QF

Creation of an all-weather facility comprising of a polo arena, conversion of farm buildings into stables, new fencing, landscaping, lighting scheme, new car parking area

Local Authority
North Kesteven District Council
Type
Full planning consent (Full Application)
Decision
Approved (Approved)
Application Received
20/12/2019
Application Validated
06/01/2020
Conversion Agricultural Landscaping Fence Stable